Q1 2016
Rijksvastgoedbedrijf invites tenders
-
Q3 2016
Tender awarded to the ‘Bajeskwartier Amsterdam’ plan
-
Q2 2017
Development of plan
-
Q2 2018
Development of plan
-
Q3 2019
Start of demolition of 5 towers
-
Q2 2020
End of demolition work
-
Q2 2020
Construction of bridges on extended Amstelstroomlaan
-
Q3 2020
Construction of railway underpass on Amstelstroomlaan
-
Q1 2021
Start construction of Spinoza20first school and sports hall
-
Q2 2021
Start construction underground car park/mobility hub
-
Q3 2021
Hotel Jansen and rented homes for De Alliantie
Start construction: october 2021
-
Q4 2021
Sneak preview of first owner-occupied homes, building The Robin
-
Q2 2022
Start sale The Robin
-
Q3 2022
Start sale The Jay (upper floors)
Start construction The Finch
-
Q4 2022
Start sale The Ruby
Start construction The Robin
-
Q1 2023
Start construction The Jay
-
Q2 2023
Start construction The Ruby
Start construction The Starling
-
Q3 2023
Expected completion Hotel Jansen / social housing
-
Q4 2023
Start construction The Emerald
-
Q1 2024
Expected completion The Finch
Start sale The Stern
Start sale The Cardinal
Start sale The Oriole
-
Q2 2024
Start sale The Emerald
-
Q3 2024
Expected completion The Jay
Start construction Green Tower
Start construction Main Building
Start construction The Stern
Start construction The Cardinal
-
Q4 2024
Expected completion The Robin
Start construction The Oriole
-
Q2 2025
Expected completion The Ruby
-
Q4 2025
Expected completion The Starling
Expected completion Green Tower
Expected completion Main Building
Expected completion The Stern
Expected completion The Cardinal
-
Q3 2026
Expected completion The Emerald
-
Q4 2026
Expected completion The Oriole